Discovery Park Construction Update Dec 2016

Tower M, 4th Floor level Slab Work in Progress
Tower L, Lower Basement Slab Work in Progress
Tower K, Structure Work & Brickwork Completed, Railing Work in Progress. Plaster work at 1st Floor is also in progress
Tower K - Plaseter work in progress
Tower K - Plaseter work in progress
Tower J, Ground Floor to 12th Floor Brickwork Blockwork Completed, 13th Floor Brickwork in progress, Ground, 1st & 4th Floor Plaster Work in Progress
Tower J – Plaster Work in Progress
Tower J - Fixing kitchen mess
Tower J - Finishing Plaster on wall tower
Tower H, Ground Floor to 6th Brickwork Completed, 7th Floor Brickwork in progress
Tower G, Ground, 1st & 4th Floor Brickwork Completed, 3rd Floor Brickwork in progress
Tower F, Ground Floor to 2nd Floor Brickwork Completed, 3rd Floor Brickwork in progress
Tower B, 6th Floor Level Slab Work in Progress, 3rd Floor Brickwork in progress
Tower A, 9th Floor Level Slab Work in Progress, Ground to 5th Floor Brickwork Completed, 6th Floor Brickwork work in progress