Discovery Park Construction Update Dec 2017

TOWER A • 15TH FLOOR SLAB CASTED. • TERRACE COLUME CASTING WORKS IN PROGRESS. • GROUND TO 14TH FLOOR BRICKWORKS COMPLETED. • RAILING WORKS IN PROGRESS • 48/88 FLATS INTERNAL PLASTER WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS
TOWER B • 15TH FLOOR SLAB COMPLETED. • 1ST TO 12TH FLOOR BRICKWORKS COMPLETED. • RAILING WORKS IN PROGRESS • 64/142 FLATS INTERNAL PLASTER WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS
TOWER F • 283/300 FLATS RAILING WORKS COMPLETED. • GROUND TO 15TH FLOOR INTERNAL PLASTER COMPLETED • EXTERNAL PLASTER WORKS COMPLETED • 75/90 FLATS IPS FLOORING WORKS COMPLETED. • TOILET DADO-30/90 FLATS, TOILET FLOOR-26/90 FLATS, D&D-24/90 FLAT
TOWER G • 250/330 RAILING WORKS IS COMPLETED. • GROUND – 15th FLOOR INTERNAL PLASTER COMPLETED. • EXTERNAL PLASTER WORKS COMPLETED • 84/90 FLATS IPS FLOORING WORKS COMPLETED. • 30/90 FLATS TOILET DADO, 30/90 TOILET FLOOR, 30/90 D&D TILING WORK
TOWER H • 240/300 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • GROUND TO 15TH FLOOR INTERNAL PLASTER COMPLETED. • EXTERNAL PLASTER WORKS COMPLETED • 86/90 FLATS IPS FLOORING WORKS COMPLETED. • 51/90 FLATS - TOILET DADO, 45/90 TOILET FLOOR, 42
TOWER J • 228/258 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • 2ND TO 15TH FLOOR INTERNAL PLASTER COMPLETED. • 80% EXTERNAL PLASTER WORKS COMPLETED, REST IN PROGRESS. • 72/86 FLATS IPS FLOORING WORKS COMPLETED. • 15/86 FLATS - TOILET DADO, 12
TOWER K • 1ST TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. REST IN PROGRESS. • EXTERNAL PLASTER WORKS COMPLETED • 52/56 FLATS IPS WORKS COMPLETED • 42/56 FLATS TOILET DADO, 25/56 FLATS TOILET FLOOR, 16/56 FLATS D&D TILLING WORKS COMPLETED. •
TOWER L • 4TH FLOOR SLAB CASTING WORKS COMPLETED. • 1ST TO 3RD FLOOR BRICKWORKS COMPLETED
TOWER M • 08TH FLOOR SLAB WORKS COMPLETED. • 1ST TO 3RD FLOOR BRICKWORKS COMPLETED.