Discovery Park Construction Update Jan 2018

TOWER A • TERRACE SLAB CASTED. • GROUND TO 14TH FLOOR BRICKWORKS COMPLETED. • RAILING WORKS IN PROGRESS • 60/88 FLATS INTERNAL PLASTER WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS
TOWER B • 17TH FLOOR SLAB COMPLETED. • 1 ST TO 12TH FLOOR BRICKWORKS COMPLETED. • RAILING WORKS IN PROGRESS • 72/142 FLATS INTERNAL PLASTER WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS
TOWER F • 283/300 FLATS RAILING WORKS COMPLETED. • GROUND TO 15TH FLOOR INTERNAL PLASTER COMPLETED • 90/90 FLATS IPS FLOORING WORKS COMPLETED. • TOILET DADO-42/90 FLATS, TOILET FLOOR36/90 FLATS, D&D-30/90 FLATS TILLING WORKS COMPLETED • BALCONY
TOWER G • 310/330 RAILING WORKS COMPLETED. • 90/90 FLATS IPS FLOORING WORKS COMPLETED. • 31/90 FLATS TOILET DADO, 31/90 TOILET FLOOR, 30/90 D&D TILING WORKS COMPLETED • 130 / 330 NOS. BALCONY CILL, 80 / 90 FLATS KITCHEN COUNTER STONE WORKS COMPLET
TOWER H • 295/300 RAILING WORKS COMPLETED, REST IN PROGRESS. • 86/90 FLATS IPS FLOORING WORKS COMPLETED. • 51/90 FLATS - TOILET DADO, 45/90 TOILET FLOOR, 48/90 D&D TILLING WORKS COMPLETED • 200/300 NOS. BALCONY CILL, 36/90 FLATS KITCHEN COUNTER ST
TOWER J • 228/258 RAILING WORKS COMPLETED, REST IN PROGRESS. • 1 ST TO 15TH FLOOR INTERNAL PLASTER COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED, REST IN PROGRESS. • 80/86 FLATS IPS FLOORING WORKS COMPLETED. • 36/86 FLATS - TOILET DADO, 36/8
TOWER K • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. REST IN PROGRESS. • EXTERNAL PLASTER WORKS COMPLETED • 52/56 FLATS IPS WORKS COMPLETED • 42/56 FLATS TOILET DADO, 35/56 FLATS TOILET FLOOR, 25/56 FLATS D&D TILLING WORKS COMPLETED.
TOWER L • 7 TH FLOOR SLAB CASTING WORKS COMPLETED. • 1 ST TO 3RD FLOOR BRICKWORKS COMPLETED
TOWER M • 09TH FLOOR SLAB WORKS COMPLETED. • 1 ST TO 3RD FLOOR BRICKWORKS COMPLETED.