Discovery Park Construction Update July 2017

TOWER A - 14TH FLOOR LEVEL SLAB CASTED. • 14TH TO 15TH FLOOR COLUMN CASTING WORKS IN PROGRESS. • GROUND TO 9TH FLOOR BRICKWORKS COMPLETED. • 10TH FLOOR BRICKWORKS IN PROGRESS. • 10TH FLOOR INTERNAL PLASTER COMPLETED. • 11TH FLOOR INTERNAL PLASTE
TOWER B - 11TH FLOOR LEVEL SLAB COMPLETED.• 12TH FLOOR LEVEL SLAB WORKS IN PROGRESS. • 1ST TO 8TH FLOOR BRICKWORKS COMPLETED. • INTERNAL PLASTER WORKS IN PROGRESS
TOWER F - BRICKWORKS COMPLETED.• 225/300 RAILING WORKS IS COMPLETED.• 14TH FLOOR INTERNAL PLASTER COMPLETED.• 15TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS.• 30% EXTERNAL PLASTER WORKS COMPLETED • 12TH FLOOR IPS WORKS COMPLETED. • STONE WORKS
TOWER G - 215/330 RAILING WORKS COMPLETED • 14TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 15TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS.• 35% EXTERNAL PLASTER WORKS COMPLETED • 15TH FLOOR IPS WORKS COMPLETED • STONE WORKS IN PROGRESS.• INTERN
TOWER H - 150/300 RAILING WORKS COMPLETED • GROUND TO 9TH FLOOR INTERNAL PLASTER WORKS COMPLETED.• 10TH & 11TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS. • 35% EXTERNAL PLASTER WORKS COMPLETED • 25/90 FLAT IPS WORKS COMPLETED • STAIRCASE KOTA STO
TOWER J - BRICKWORKS COMPLETED.• 228/258 RAILING WORKS COMPLETED • INTERNAL PLASTER WORKS COMPLETED FOR 1ST & 4TH TO 11TH FLOOR AND 2 FLATS ON GF.• 30% EXTERNAL PLASTER WORKS COMPLETED • IPS WORKS IN PROGRESS • 52/258 BALCONY CILL STONE WORKS CO
TOWER K - 168/168 RAILING WORKS COMPLETED • INTERNAL PLASTER COMPLETED FOR 1ST, 4TH TO 6TH, 3 FLATS ON 7TH, 3 FLATS ON 8TH, 9TH TO 15TH FLOOR.• 60% EXTERNAL PLASTER WORKS COMPLETED • IPS WORKS COMPLETED FOR 3 FLATS ON 1ST, 4TH TO 6TH, 3 FLATS ON 7TH
TOWER L - 2ND FLOOR LEVEL SLAB CASTING WORKS IN PROGRESS.
TOWER M - 07TH FLOOR LEVEL SLAB WORKS IN PROGRESS.• 1ST & 2ND FLOOR BRICKWORKS IN PROGRESS.