Discovery Park Construction Update March 2017

TOWER A - 10th floor level slab casted. • 10th - 11th floor column casting works is in progress. • Ground - 3 rd floor & 5th - 7th floor brick works complete. • 8th floor brick works is in progress.
TOWER B - 7th floor level slab complete. • 7th - 8th floor column casting works is in progress • 1 st - 4th floor brick works complete.
TOWER F - Ground to 12th floor brick works is complete. • 14th - 15th floor brick works is in progress. • Railing works is in progress. • Ground - 3 rd Floor Internal Plaster works complete. • 4th floor Internal Plaster works is in progress. • E
TOWER G - Ground - 11th floor brickworks complete. • 12th - 14th floor brickworks is in progress. • Railing works is in progress. • Ground - 5 th floor internal plaster works complete. • 6 th - 7 th floor internal plaster works is in progress. •
TOWER H - Ground - 14th floor brickworks complete. • 15th floor brickwork is in progress. • Ground - 3 rd floor plaster complete. • 4 th, 6th & 7 th floor internal plaster is in progress. • Ground - 3 rd Plumbing shaft external plaster completed.
TOWER J - All Brickwork complete except Shaft • Railing fixing works in progress. • 46 / 86 flats internal plaster works complete. • External plaster works in progress on balcony area Front side.
TOWER K - 3 rd floor 50%, 4 External shaft brickworks balance. Rest all brickworks complete. • Railing works is in progress. • 35 / 56 Flats internal plaster works complete. • External plaster works in progress on balcony area Front side. • 10 / 5
TOWER L - Upper Basement Roof level slab casting works is in progress.
TOWER M - 04th floor level slab works is in progress.
INTERNAL PLASTER WORKS IS IN PROGRESS
BRICKWORKS IS IN PROGRESS
PLUMBING WORKS IS IN PROGRESS
STAIRCASE KOTA STONE WORKS IS IN PROGRESS
PLUMBING WORKS IS IN PROGRESS