Discovery Park Construction Update March 2018

TOWERS – F, G, & H FRONT ELEVATION
TOWER - K • GROUND TO 15TH FLOOR INTERNAL PLASTER COMPLETED • 100% EXTERNAL PLASTER WORKS COMPLETED • 56/56 FLATS IPS FLOORING COMPLETED • 52/56 FLATS DADO WORKS COMPLETED, 52/56 FLATS TOILET FLOORING WORKS COMPLETED AND 50/56 D&D TILING WORKS COM
TOWER - J • 228/258 RAILING WORKS COMPLETED • 1 ST TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 100% EXTERNAL PLASTER WORKS COMPLETED • 82/86 FLATS IPS FLOORING COMPLETED • 58/86 FLATS DADO WORKS COMPLETED, 58/86 FLATS TOILET FLOORING WORK
TOWER - H • 289/300 RAILING WORKS COMPLETED • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 100% EXTERNAL PLASTER WORKS COMPLETED • 86/90 FLATS IPS FLOORING COMPLETED • 66/90 FLATS DADO WORKS COMPLETED, 66/90 FLATS TOILET FLOORING WORK
TOWER - G • 315/330 RAILING WORKS COMPLETED • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 100% EXTERNAL PLASTER WORKS COMPLETED • 90/90 FLATS IPS FLOORING COMPLETED • 60/90 FLATS DADO WORKS COMPLETED, 60/90 FLATS TOILET FLOORING WOR
TOWER - F • 285/330 RAILING WORKS COMPLETED • GROUND TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 100% EXTERNAL PLASTER WORKS COMPLETED • 90/90 FLATS IPS FLOORING COMPLETED • 72/90 FLATS DADO WORKS COMPLETED, 72/90 FLATS TOILET FLOORING WOR
TOWER - L 8 TH FLOOR SLAB WORKS COMPLETED. 1 ST TO 4TH FLOOR BRICK WORKS COMPLETED.
TOWER - M 11TH FLOOR SLAB CASTED. 1 ST TO 5TH FLOOR BRICK WORKS COMPLETED.
TOWER - A • TERRACE SLAB CASTED. • GROUND TO 14TH FLOOR BRICK WORKS COMPLETE • 72/88 FLATS INTERNAL PLASTER WORKS COMPLETED • 80% EXTERNAL PLASTER WORKS COMPLETED • 22/88 FLATS IPS FLOORING WORKS COMPLETED • RAILING FIXING WORKS IN PROGRESS.
TOWER - B • 18TH FLOOR LEVEL SLAB COMPLETED • 1 ST TO 15TH FLOOR BRICK WORKS COMPLETE • 88/142 FLATS INTERNAL PLASTER WORKS COMPLETED • 30% EXTERNAL PLASTER WORKS COMPLETED • 22/88 FLATS IPS FLOORING WORKS COMPLETED • RAILING FIXING WORKS IN
EWS UNITS - WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
CLUB STRUCTURE WORKS IN PROGRESS
MAIN ENTRANCE - WORKS IN PROGRESS
MAIN ENTRANCE - WORKS IN PROGRESS
PAVER WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
TOWER – H LOBBY FALSE CEILING WORKS IN PROGRESS
PAVER ROAD WORKS IN PROGRESS
TOWER - H SAMPLE FLAT
TOWER - H SAMPLE FLAT
TOWER - H SAMPLE FLAT
TOWER - H SAMPLE FLAT