Discovery Park Construction Update NOV 2016

Tower M, 3rd Floor Level Slab Work in Progress
Tower L, Lower Bsement Slab Work in Progress
Tower K, Structure Work & Brickwork Completed, Railing Work in Progress
Tower J, Ground to 10th Floor Brickwork & Blockwork Completed, 11th Floor Brickwork in Progress, 4th Floor Plaster Work in Progress
Tower H, Ground to 3rd Floor Brickwork Completed, 4th Floor Brickwork in Progress
Tower G, Ground Floor Brickwork Completed, 1st Floor Brickwork in Progress
Tower F, Ground Floor Brickwork Completed, 1st Floor Brickwork in Progress
Tower B, 5th Floor Level Slab Work in Progress, 1st Floor Brickwork in Progress
Tower A, 9th Floor Slab Work in Progress, Ground to 4th Floor Brickwork Completed, 5th floor Brickwork in progress