In order to give you a better experience, we are renovating our website. However, please note that the data mentioned on the website is still being updated. For accurate and upto date information, please contact our team at customercare@bptp.com.
In order to give you a better experience, we are renovating our website. However, please note that the data mentioned on the website is still being updated. For accurate and upto date information, please contact our team at customercare@bptp.com.
Slideshow Image 1

Discovery Park Construction Update Nov 2017

TOWER A • 15TH FLOOR SLAB CASTED. • TERRACE COLUME CASTING WORKS IN PROGRESS. • GROUND TO 14TH FLOOR BRICKWORKS COMPLETED. • RAILING WORKS IN PROGRESS • 42/88 FLATS INTERNAL PLASTER WORKS COMPLETED.
TOWER B • 14TH FLOOR SLAB COMPLETED. • 15TH FLOOR SLAB WORKS IN PROGRESS. • 1ST TO 12TH FLOOR BRICKWORKS COMPLETED. • RAILING WORKS IN PROGRESS • 48/142 FLATS INTERNAL PLASTER WORKS COMPLETED.
TOWER F • 283/300 FLATS RAILING WORKS COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED • 52/90 FLATS IPS FLOORING WORKS COMPLETED. • TOILET DADO-18/90 FLATS, TOILET FLOOR-18/90 FLATS, D&D-16/90 FLATS TILLING WORKS COMPLETED • BALCONY CILL-80/30
TOWER G • 223/330 RAILING WORKS IS COMPLETED. • GROUND – 15th INTERNAL PLASTER COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED • 84/90 FLATS IPS FLOORING WORKS COMPLETED. • 21/90 FLATS TOILET DADO, 21/90 TOILET FLOOR, 21/90 D&D TILING WORKS
TOWER H • 230/300 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • GROUND TO 15TH FLOOR INTERNAL PLASTER COMPLETED. • 80% EXTERNAL PLASTER WORKS COMPLETED • 84/90 FLATS IPS FLOORING WORKS COMPLETED. • 51/90 FLATS - TOILET DADO, 45/90 TOILET FLOOR
TOWER J • 228/258 RAILING WORKS IS COMPLETED, REST IN PROGRESS. • 2 FLATS ON GROUND FLOOR, 1ST, 3FLATS ON 2ND FLOOR 3RD TO 15TH FLOOR INTERNAL PLASTER COMPLETED. • 75% EXTERNAL PLASTER WORKS COMPLETED • 37/86 FLATS IPS FLOORING WORKS COMPLETED.
TOWER K • 1ST TO 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. REST IS IN PROGRESS. • 95% EXTERNAL PLASTER WORKS COMPLETED • 52/56 FLATS IPS WORKS COMPLETED • 35/86 FLATS TOILET DADO, 10/86 FLATS TOILET FLOOR, 6/86 FLATS D&D TILLING WORKS COMPLETED
TOWER L • 4TH FLOOR SLAB CASTING WORKS COMPLETED. • GROUND FLOOR BRICKWORKS COMPLETED
TOWER M • 08TH FLOOR SLAB WORKS IN PROGRESS. • 3RD FLOOR BRICKWORKS IN PROGRESS.