Park 81 Construction Update July 2017

AQ1-01 TO 17 EXTERNAL PAINTING & ROAD WORKS IN PROGRESS
AQ-8 TO 24 FLOORING & EXTERNAL PAINTING WORKS IN PROGRESS
CL3-01 TO 06 EXTERNAL PLASTER WORKS IN PROGRESS
CL4-01 TO 06 INTERNAL & EXTERNAL PAINTING WORKS IN PROGRESS
CL4-07 TO 12 FLOORING WORKS IN PROGRESS
CL8-01 TO 03 INTERNAL & EXTERNAL PLASTER WORKS IN PROGRESS
CL8-04 TO 06A INTERNAL PLUMBING WORKS IN PROGRESS
CL8-04 TO 06A INTERNAL PLUMBING WORKS IN PROGRESS