Slideshow Image 1

Park 81 Construction Update Nov 2017

AQ2-01 to 08 EXTERNAL & INTERNAL PLASTER AND IPS FLOORING WORKS IN PROGRESS
AQ5-06 TO 12A INTERNAL PLASTER WORKS IN PROGRESS
AQ5-14 to 21 EXTERNAL & INTERNAL PLASTER WORKS IN PROGRESS
AQ5-22 to 29 EXTERNAL & INTERNAL PLASTER AND RAILING FIXING WORKS IN PROGRESS
CL4-01 to 06 EXTERNAL PAINTING WORKS IN PROGRESS
CL4-07 to 12 INTERNAL PLASTER AND TILES FIXING WORKS IN PROGRESS
CL8-04 to 06A TILES FIXING WORKS IN PROGRESS
OMEGA 12-01 TO 06 MUMTY SLAB RCC WORKS IN PROGRESS
OMEGA 28- 02 TO 10 EXTERNAL & INTERNAL PLASTER, BRICK COBBA AND RAILING FIXING WORKS IN PROGRESS
OMEGA 28-01 TO 09 EXTERNAL PLASTER WORKS IN PROGRESS