Park 81 Construction Update Oct 2017

CL4-01 TO 06 EXTERNAL & INTERNAL PAINTING WORKS IN PROGRESS
CL8-04 TO 06A TILING WORKS IN PROGRESS
AQ2-01 to 08 EXTERNAL & INTERNAL PLASTER, R.C.C GRID SLAB, DOOR FRAME FIXING WORKS IN PROGRESS
AQ5-06 to 12A BRICKS, R.C.C., DOOR FRAME FIXING WORKS IN PROGRESS
AQ5-14 to 21 INTERNAL PLASTER, R.C.C., DOOR FRAME FIXING WORKS IN PROGRESS
AQ5-22 to 29 INTERNAL & EXTERNAL PLASTER, WATER TANK BRICK WORKS IN PROGRESS
CL3-01 to 06 BOUNDARY WALL BRICK WORKS & TILING WORKS IN PROGRESS
CL4-07 to 12 INTERNAL PLASTER & TILING WORKS IN PROGRESS
CL8-01 to 03 INTERNAL PLASTER & R.C.C. GRID SLAB WORKS IN PROGRESS
OMEGA 28-02 TO 10 EXTERNAL PLASTER & BALCONY RAILING FIXING WORKS IN PROGRESS
OMEGA 12-01 TO 06 MUMTY R.C.C. WORKS IN PROGRESS
OMEGA 28-01 TO 09 EXTERNAL PLASTER & BOUNDARY WALL BRICK WORKS IN PROGRESS