Park Elite Floors I and II Construction Update Aug 2017

E Block

E85 - BLOCK E15-9 TO 12
BLOCK-E 24 ROW MUMTY SLAB CASTING WORKS IN PROGRESS
BLOCK-E115-E33-2 TO 7 EXTERNAL SERVICES WORKS IN PROGRESS
BLOCK-E115-E42-1 TO 12 B CAR PARKING AREA WORKS IN PROGRESS
BLOCK-E115-EXTERNAL PAINTING WORKS IN PROGRESS
E-85 BLOCK E37-9- TO 17 EXTERNAL PAINTING WORKS IN PROGRESS

H Block

BLOCK-H79-H34 TO 41 FINAL FINISHING WORKS IN PROGRESS
BLOCK-H79-H4-1 to 21
H79-H7-1 to 3

L Block

L15 (14 to 23) FINISHING WORKS IN PROGRESS
L15 (2 to 11)
L15-2 TO 11 BLOCK FLOOR TILES FIXING WORKS IN PROGRESS

LM Block

LM-Block
BLOCK LM4-38 TO 58 REAR SIDE EXTERNAL PLASTER WORKS IN PROGRESS
BLOCK LM4-49 TO 61 BRICK COBA WORKS IN PROGRESS
BLOCK LM4-49 TO 61 FLOOR TILES FIXING WORKS IN PROGRESS
BLOCK LM4-38 TO 58 STAIRCASE KOTA STONE FIXING WORKS IN PROGRESS
BLOCK LM4-49 TO 61 WALL TILES FIXING WORKS IN PROGRESS

M Block

BLOCK M11-1 TO 9 EXTERNAL PAINTING WORKS IN PROGRESS
BLOCK M11- 1 TO 9 INTERNAL PAINTING WORKS IN PROGRESS
BLOCK M11-1 TO 9 KOTA GRINDING WORKS IN PROGRESS
BLOCK M11-1 TO 9 TEXTURE PAINTING WORKS IN PROGRESS

P Block

P-BLOCK P4-02 TO 60 FLOORING & INTERNAL PLASTER, INTERNAL PAINTING & EXTERNAL PAINTING WORKS IN PROGRESS
P-BLOCK EXTERNAL PAINTING WORKS IN PROGRESS
P-BLOCK INTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK INTERNAL PAINTING WORKS IN PROGRESS
P-BLOCK INTERNAL PAINTING WORKS IN PROGRESS
P-BLOCK INTERNAL PAINTING WORKS IN PROGRESS
P-BLOCK KOTA STONE GRINDING WORKS IN PROGRESS
P-BLOCK P8-02 TO 16 EXTERNAL PLASTER WORKS IN PROGRESS

PA Block

PA-238 TO 241 EXTERNAL PLASTER WORKS IN PROGRESS
PA-234 TO 241 PARAPET PLASTER WORKS IN PROGRESS

PC Block

PC-77 TO 85 INTERNAL AND EXTERNAL PAINTING AND DOOR SHUTTER FIXING WORKS IN PROGRESS
PC-60 TO 76 INTERNAL PLUMBING WORKS IN PROGRESS
PC-60 TO 76 WATER TANK PLATFORM WORKS IN PROGRESS
PC-77 TO 84 STAIRCASE RAILLING WORKS IN PROGRESS
PC-85 TO 93 CHAMBER PLASTER WORKS IN PROGRESS
PC-90 TO 93 INTERNAL PLASTER WORKS IN PROGRESS

PE Block

PE-86 TO PE-95 EXTERNAL PLASTER WORKS IN PROGRESS
PE-86 TO PE-95 EXTERNAL PLASTER WORKS IN PROGRESS
PE-43 EXTERNAL PLASTER WORKS IN PROGRESS
PE-43 TO PE-42 EXTERNAL PLASTER WORKS IN PROGRESS
PE-75 TO PE-83 INTERNAL PLASTER WORKS IN PROGRESS
PE-118 TO PE-125 BRICK WORKS IN PROGRESS
PE-172 TO PE-178 BRICK WORKS IN PROGRESS
PE-BLOCK IPS FLOORING WORKS IN PROGRESS