Park Elite Floors I and II Construction Update March 2018

E Block

BLOCK E-21 E24-04-07 INTERNAL FLOORING WORKS IN PROGRESS
BLOCK E-85 E40-01 TO 23 EXTERNAL PAINT, FLOORING AND INTERNAL PAINTING WORKS IN PROGRESS
BLOCK E-115 E72 TO E-84 EXTERNAL PAINT AND FLOORING WORKS IN PROGRESS
BLOCK E-115 E72 ROW TILE FIXING WORKS IN PROGRESS

H Block

BLOCK H-79, H3-01 TO 09 ROW EXTERNAL PAINTING WORKS IN PROGRESS
BLOCK H-79, H3-01 TO 09 ROW TILING WORKS IN PROGRESS

LM Block

LM4-38 TO 58 FLOORING, DOOR HARDWARE AND PAINTING WORKS IN PROGRESS
LM4-38 TO 58 FLOORING WORKS IN PROGRESS
LM4-38 TO 58 DOOR HARDWARE FIXING WORKS IN PROGRESS

PA Block

PA-228 TO PA-241 EXTERNAL & INTERNAL PLASTER, FLOORING AND INTERNAL PLUMBING WORKS IN PROGRESS
PA-242 TO PA-247 EXTERNAL & INTERNAL PLASTER, FLOORING AND PLUMBING WORKS IN PROGRESS

PC Block

PC-37 TO PC-52 TILING & INTERNAL PLUMBING WORKS IN PROGRESS
PC-60 TO PC-76 INTERNAL DOOR SHUTTER, UPVC DOOR AND INTERNAL PAINTING WORKS IN PROGRESS
PC-77 TO PC-93 UPVC GLAZING, ELECTRICAL WIRING, CHINAWARE AND INTERNAL PAINTING WORKS IN PROGRESS

P Block

P-BLOCK (P-27 & P-28) BRICK COBA, PLUMBING, EXTERNAL & INTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK P4-02 TO P4-60 EXTERNAL & INTERNAL PAINTING WORKS IN PROGRESS
P-BLOCK P5-01 TO P5-08 DOOR FRAME FIXING WORKS IN PROGRESS
P-BLOCK P5-09 TO P5-12 BRICK COBA, EXTERNAL PLASTER, ELECTRICAL AND PLUMBING WORKS IN PROGRESS
P-BLOCK P5-09 TO P5-12 BRICK COBA AND EXTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK P6-02 TO P6-10 EXTERNAL AND INTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK P7-02 TO P7-24 INTERNAL AND EXTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK P8-01 TO P8-23 ELECTRICAL, EXTERNAL AND INTERNAL PLASTER WORK IN PROGRESS
P-BLOCK P10-02 TO P10-16 TILE FIXING, GRADE SLAB, BRICK COBA, EXTERNAL AND INTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK P10-27 TO P10-31 TILE FIXING, ELECTRICAL, PLUMBING, BRICK COBA, INTERNAL AND EXTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK P11-02 & P11-03 TILE FIXING, PLUMBING, EXTERNAL AND INTERNAL PLASTER WORKS IN PROGRESS
P-BLOCK P15-02 TO P15-10 EXTERNAL PLASTER, ELECTRICAL AND PLUMBING WORKS IN PROGRESS
P-BLOCK P15-12 TO P15-16 EXTERNAL PLASTER AND ELECTRICAL WORKS IN PROGRESS
P-BLOCK P17-01 TO P17-04 EXTERNAL PLASTER, ELECTRICAL AND BRICK COBA WORK IN PROGRESS