Park Elite Floors I and II Construction Update NOV 2016

Block-P, Internal finishing work in progress
Block-M, External painting & internal painting work in progress
Block-LM, Pargola casting,railing fixing & intrnal work in progress
Block-L37, External texture painting & internal finishing work in progress
Block-H 79, Extrnal painting & intrnal finishing in progress
Block-E 115, External painting & Internal finshing work in progress
Block-E 85, Extrnal plaster work in progress
Internal finishing
Brick work in progress
Boundarywall brick work in progress