Park Elite Premium Construction Update April 2018

FRONT ELEVATION
TOWERS -A, B, D & C
TOWER- A • 80% TERRACING WORKS COMPLETED. • 54/60 UNITS IPS FLOORING WORKS COMPLETED. • 20% STONE & TILES WORKS COMPLETED. • 20% LIFT WORKS COMPLETED. • 30% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COM
TOWER- B • 36/40 UNITS IPS FLOORING WORKS COMPLETED. • 10% STONE & TILES WORKS COMPLETED. • 20% LIFT WORKS COMPLETED. • 30% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- C • 95% EXTERNAL PLASTER WORKS COMPLETED. • 5% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 20% LIFT WORKS COMPLETED. • 20% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WOR
TOWER- D • 98% External Plaster works Completed. • 5% Internal Putty/Paint works Completed. • 38/40 Units IPS Flooring works Completed. • 20% Lift works completed. • 100% Fire Fighting works completed. • 80% External Storm, Sewerage & water su
TOWER- G • 100% External Plaster works Completed. • 50% stone & tiles works completed. • 100% IPS Flooring works Completed. • 10% Internal Putty/Paint works Completed. • 10% Lift works completed. • 30% Fire Fighting works completed. • 80% Ex
TOWER- J • 100% External Plaster works Completed. • 20% Stone & Tiles works completed. • 100% IPS Flooring works Completed. • 10% Internal Putty/Paint works Completed. • 10% Lift works completed. • 30% Fire Fighting works completed. • 80% Ex
TOWER- K • 100% External Plaster works Completed. • 100% IPS Flooring works Completed. • 10% Internal Putty/Paint works Completed. • 10% Lift works completed. • 30% Fire Fighting works completed. • 70% External Storm, Sewerage & water supply w
EWS TOWER • 100% EXTERNAL PLASTER WORKS COMPLETED. • 55/56 UNITS IPS FLOORING WORKS COMPLETED. • 25% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 50% FIRE FIGHTING WORKS COMPLETED. • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
VILLAS 10-19 • 95% INTERNAL PLASTER WORKS COMPLETED. • 100% EXTERNAL PLASTER WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 30% STONE & TILES WORKS COMPLETED. • 70% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
FIRE STAIRCASE WORKS IN PROGRESS
KERB STONE WORKS IN PROGRESS
SWIMMING POOL WORKS IN PROGRESS