Parklands Pride Construction Update Oct 2017

1PB-32 TO 25 INTERNAL WIRING WORKS IN PROGRESS
2PA-17 TO 24 UPVC DOOR AND WINDOW FIXING WORKS IN PROGRESS
3PA-114 TO 120 FALL CEILLING WORKS IN PROGRESS
4PA-134 TO 123 EXTERNAL PAINTING WORKS IN PROGRESS
5PA-150 TO 165 FLOORING WORKS IN PROGRESS
6PA-194 TO 207 INTERNAL & EXTERNAL PLUMBING AND GRADE SLAB WORKS IN PROGRESS
7PB-48 TO 56 EXTERNAL CONNECTIONS & DOOR HARDWARE FIXING WORKS IN PROGRESS
8PB-57 TO 67 FLOORING AND UPVC DOOR WINDOW FIXING WORKS IN PROGRESS
9PB-57 TO 67 STAIRCASE STONE WORKS IN PROGRESS
10PB-65 TO 67 FLOORING WORKS IN PROGRESS
11PB-67 INTERNAL PLUMBING TESTING WORKS IN PROGRESS
12PB-69 TO 80 TARRACE RING LINE PLATFORM WORKS IN PROGRESS
13PB-69 T0 86 TANK PLATFORM WORKS IN PROGRESS
14PB-69 TO 74 FLOORING WORKS IN PROGRESS
15PB-69 TO 86 FRONT VERANDAH BRICK WORKS IN PROGRESS
16PB-69 TO 86 INTERNAL PLUMBING WORKS IN PROGRESS
17PB-106 TO 127 EXTERNAL PLASTER WORKS IN PROGRESS
18PB-186 TO 205 EXTERNAL PUTTY WORKS IN PROGRESS
19PB-186 TO 205 INTERNAL PAINTING WORKS IN PROGRESS
20PB-186 TO 205 STAIRCASE STONE WORKS IN PROGRESS
21PB-196 TO 200 DOOR CILL STONE WORKS IN PROGRESS
22PB-200 TO 205 FRONT VERANDAH STONE AND TILE WORKS IN PROGRESS
23PB-208 TO 219 INTERNAL & EXTERNAL DOOR WINDOW FIXING WORKS IN PROGRESS
24PB-220 TO 231 INTERNAL DOOR FIXING WORKS IN PROGRESS
25PB-220 TO 231 INTERNAL PUTTY WORKS IN PROGRESS
26PB-230 FRONT VERANDAH WORKS IN PROGRESS