Amstoria Construction Update April 2018

NPR ACCESS PROJECT BRANDING IN PROGRESS
NPR ACCESS ENTRANCE PAVER WORKS IN PROGRESS
NPR ACCESS ENTRANCE FEATURE WALL WORKS COMPLETED
NPR ACCESS ENTRANCE FINISHING WORKS IN PROGRESS
NPR ENTRANCE GUARD ROOM FINISHING WORKS IN PROGRESS
WATER BODY FEATURE COBBLE WORKS IN PROGRESS
75 MT. ROAD ACCESS PROJECT BRANDING WORKS COMPLETED
A-56 TO A-60 EXTERNAL PAINTING WORKS IN PROGRESS
A-61 EXTERNAL PAINTING WORKS IN PROGRESS
A-61 TO A-66 EXTERNAL PAINTING WORKS IN PROGRESS
A-67 TO A-72 EXTERNAL PAINTING WORKS IN PROGRESS
A- 85 TO A-90 EXTERNAL FINISHING WORKS IN PROGRESS
A-BLOCK REAR COURTYARD PRECAST WALL FIXING WORKS IN PROGRESS
D-126 TO D-130 INTERNAL FINISHING WORKS IN PROGRESS
D-124 TO D-125 PLASTER WORKS IN PROGRESS
A-51 & A-52 FLOOR TILING WORKS IN PROGRESS
PARK 2 - HARDSCAPING WORKS ARE IN PROGRESS
PARK 4 - HARDSCAPING WORKS ARE IN PROGRESS
HORTICULTURE WORKS IN PROGRESS
CLUB HOUSE - GROUND FLOOR ROOF SLAB AND STRUCTURAL STEEL COLUMNS ERECTION WORKS IN PROGRESS