Amstoria Construction Update Feb 2018

FARM VILLA

NPR ACCESS ENTRANCE WORKS IN PROGRESS
NPR ACCESS ENTRANCE STEEL FABRICATION IN PROGRESS
75 Mt. ROAD ACCESS ENTRANCE COMPLETE
75 Mt. ROAD ACCESS ENTRY WATER BODY COMPLETE
D - 32 SLAB CASTING WORKS IN PROGRESS
D - 25 TO D - 29 EXTERNAL WORKS IN PROGRESS
D - 32 SLAB CASTING WORKS IN PROGRESS
C BLOCK PARK NO. 10 COMPLETED
C BLOCK PARK NO. 7 COMPLETED
C BLOCK PARK NO. 7 COMPLETED
CLUB HOUSE - BASEMENT ROOF COMPLETE GROUND FLOOR ROOF SHUTTERING WORKS IN PROGRESS
SECURITY CENTRE WORKS IN PROGRESS
MAIN ENTRANCE CURB STONE WORKS IN PROGRESS

NPR ACCESS ENTRANCE WORKS IN PROGRESS
NPR ACCESS ENTRANCE STEEL FABRICATION IN PROGRESS
75 Mt. ROAD ACCESS ENTRANCE COMPLETE
75 Mt. ROAD ACCESS ENTRY WATER BODY COMPLETE
A - 56 TO A - 60 EXTERNAL PAINT WORKS IN PROGRESS
D - 126 TO D - 128 TILE & STONE WORKS IN PROGRESS
A - 103 & A - 104 BRICK WORKS IN PROGRESS
A - 24 TILE & STONE WORKS IN PROGRESS
A - 22 & A - 23 EXTERNAL PAINT WORKS IN PROGRESS
A - 61 TO A - 66 EXTERNAL PAINT WORKS IN PROGRESS
A - 52 & A - 51 TILES & STONE WORKS IN PROGRESS
A - 67 TO A - 72 EXTERNAL PAINT WORKS IN PROGRESS
A - 61 & A - 62 EXTERNAL PAINT WORKS IN PROGRESS
A - 52 TILE FIXING WORKS IN PROGRESS)
A - 62 TOILET COUNTER WORKS IN PROGRESS
A - 62 KITCHEN COUNTER WORKS IN PROGRESS
A - 61 INTERNAL FLOORING & DOOR WORKS IN PROGRESS
A - 61 & A - 62 ENTRANCE, FINISHING WORKS IN PROGRESS
PARK NO - 1 HARD LANDSCAPE WORKS IN PROGRESS
PAVER ROAD WORKS IN PROGRESS
A - 47 & A - 46 INTERNAL PLASTER WORKS IN PROGRESS
PARK NO - 2 HARD LANDSCAPE WORKS IN PROGRESS
A - 57 ELECTRICAL WORKS IN PROGRESS
C BLOCK PARK NO. 10 COMPLETED
C BLOCK PARK NO. 7 COMPLETED
C BLOCK PARK NO. 7 COMPLETED
CLUB HOUSE - BASEMENT ROOF COMPLETE GROUND FLOOR ROOF SHUTTERING WORKS IN PROGRESS
SECURITY CENTRE WORKS IN PROGRESS
MAIN ENTRANCE CURB STONE WORKS IN PROGRESS