Wall tilling work at rear (Office) entry is in progress
Tremix is in progress at Rear Area
Tiling work in drivers toilet is in progress
Staircase steps flooring at Rear entry is in Progress
Staircase painting from Ground to 3rd Floor is in Progress
Services works & false ceiling in Ground Floor lift lobby is in progress
Services and tiling works at 4th floor lift lobby are in progress
Parking Area adjacent to rear entry is ready for tremix
Painting on Ramps is in Progress
Main entrance external stone flooring is almost completed
Kota griding in basement service rooms is in progress
Closing of Services Shafts at Terrace