Park Generations Construction Update April 2018

FRONT ELEVATION
TOWER - 1 COMPLETED
TOWER - 2 • KITCHEN & TOILET COUNTER WORK IN PROGRESS • GROUND FLOOR TO 19TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PUTTY WORKS IN PROGRESS
TOWER - 3 • 95% IPS FLOORING WORKS COMPLETED • KITCHEN & TOILET COUNTER WORK IN PROGRESS • 1 ST TO 19TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 4 • RAILING WORKS IN PROGRESS • 85% EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 48/75 FLATS DADO WORKS COMPLETED • 25/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 2 ND TO 7TH FLOOR SINGLE COAT INTERNA
TOWER - 5 • RAILING WORKS IN PROGRESS • 90% EXTERNAL PLASTER COMPLETED • 70/75 FLATS IPS FLOORING WORKS COMPLETED • 72/75 FLATS DADO WORKS COMPLETED • 56/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGR
TOWER - 6 • RAILING WORKS COMPLETED • INTERNAL PLASTER WORKS IN PROGRESS • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 63/75 FLATS DADO WORKS COMPLETED • 56/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 2 N
EXTERNAL DEVELOPMENT
EXTERNAL DEVELOPMENT
EXTERNAL DEVELOPMENT
EXTERNAL DEVELOPMENT
METERS INSTALED
M.S. FACADE CANOPY WORKS IN PROGRESS
LIFT TESTING WORKS IN PROGRESS
PODIUM WORKS IN PROGRESS
PODIUM WORKS IN PROGRESS