Park Generations Construction Update Dec 2017

PARK GENERATIONS
TOWER – 1 • EXTERNAL PLASTER WORKS COMPLETED. • ALL TILES & STONE WORK COMPLETED. • PUTTY WORKS IN PROGRESS AND DONE FROM 1ST TO 19TH FLOOR SINGLE COAT
TOWER – 2 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • VITRIFIED FLOORING IN 73 FLATS OUT OF 75 COMPLETED. • TYP. LIFT LOBBY FLOORING WORKS COMPLETED FROM GROUND FLOOR TO 19TH FLOOR • CLADDING WORKS COMP
TOWER – 3 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • 95% IPS FLOORING COMPLETED. • 55/75 FLATS DADO WORKS COMPLETED. • TYP. LIFT LOBBY FLOORING & CLADDING WORKS COMPLETED FROM 1ST FLOOR TO 9TH FLOOR
TOWER – 4 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 85% EXTERNAL PLASTER WORKS COMPLETED. • 74/75 FLATS IPS FLOORING COMPLETED. • 30/75 FLATS DADO WORKS COMPLETED. • 05/75 FLATS VITRIFIED FLOORING WORKS COMPLETED.
TOWER – 5 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 90% EXTERNAL PLASTER WORKS COMPLETED. • 70/75 FLATS IPS FLOORING COMPLETED. • 44/75 FLATS DADO WORKS COMPLETED. • 44/75 FLATS VITRIFIED FLOORING WORKS COMPLETED.
TOWER – 6 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • 72/75 FLAT IPS FLOORING COMPLETED. • 56/75 FLATS DADO WORKS COMPLETED. • 42/75 FLATS VITRIFIED FLOORING WORKS COMPLETED. • PUTTY WORKS IN PROGRESS