Park Generations Construction Update Jan 2018

PARK GENERATIONS
TOWER – 1 • INTERNAL PUTTY WORKS IN PROGRESS, GROUND TO 19TH FLOOR SINGLE COAT DONE • EXTERNAL PUTTY WORKS IN PROGRESS
TOWER – 2 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • VITRIFIED FLOORING COMPLETED. • KITCHEN COUNTER STONE WORKS IN PROGRESS • TOILET TILES WORKS IN PROGRESS • TYP. LIFT LOBBY FLOORING WORKS COMPLETED • INTERNAL PUTTY WORKS IN PROGRESS, GR
TOWER – 3 • 95% EXTERNAL PLASTER WORKS COMPLETED. • 95% IPS FLOORING COMPLETED. • DADO WORKS COMPLETED. • KITCHEN COUNTER STONE WORKS IN PROGRESS • TOILET TILES WORKS IN PROGRESS • TYP. LIFT LOBBY COMPLETED FROM 1ST FLOOR TO 15TH FLOOR • I
TOWER – 4 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 85% EXTERNAL PLASTER WORKS COMPLETED. • 74/75 FLATS IPS FLOORING COMPLETED. • 30/75 FLATS DADO WORKS COMPLETED. • 18/75 FLATS VITRIFIED FLOORING WORKS COMPLETED. • EXTERNAL PAINT PUTTY W
TOWER – 5 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 90% EXTERNAL PLASTER WORKS COMPLETED. • 70/75 FLATS IPS FLOORING COMPLETED. • 59/75 FLATS DADO WORKS COMPLETED. • 51/75 FLATS VITRIFIED FLOORING WORKS COMPLETED.
TOWER – 6 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • 72/75 FLAT IPS FLOORING COMPLETED. • 59/75 FLATS DADO WORKS COMPLETED. • 46/75 FLATS VITRIFIED FLOORING WORKS COMPLETED. • INTERNAL PUTTY WORKS IN