Park Generations Construction Update June 2018

FRONT ELEVATION
TOWER - 1 COMPLETED
TOWER - 2 • KITCHEN & TOILET COUNTER WORK IN PROGRESS • GROUND FLOOR TO 19TH FLOOR 2 COAT INTERNAL PUTTY WORKS IN PROGRESS • EXTERNAL PUTTY WORKS IN PROGRESS
TOWER - 3 • 100% IPS FLOORING WORKS COMPLETED • KITCHEN & TOILET COUNTER WORK IN PROGRESS • 1 ST TO 19TH FLOOR 2 COAT INTERNAL PUTTY WORK IN PROGRESS • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 4 • RAILING WORKS IN PROGRESS • 85% EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 50/75 FLATS DADO WORKS COMPLETED • 44/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 2 ND TO 13TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 5 • 95% EXTERNAL PLASTER COMPLETED • 70/75 FLATS IPS FLOORING WORKS COMPLETED • 72/75 FLATS DADO WORKS COMPLETED • 70/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 6 • RAILING WORKS COMPLETED • INTERNAL PLASTER WORKS IN PROGRESS • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 71/75 FLATS DADO WORKS COMPLETED • 69/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 2 ND TO 19TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
BOUNDARY WALL LANDSCAPING
FEATURE WALL
EXTERNAL DEVELOPMENT
EXTERNAL DEVELOPMENT
EXTERNAL DEVELOPMENT
T-19 FRONT LOBBY
EXTERNAL DEVELOPMENT
PODIUM WORKS IN PROGRESS