Park Generations Construction Update May 2018

FRONT ELEVATION
TOWER - 1 COMPLETED
TOWER - 2 • DADO WORKS COMPLETED • VITRIFIED TILING WORKS COMPLETED • LIFT LOBBY WORKS COMPLETED • KITCHEN & TOILET COUNTER WORK IN PROGRESS • GROUND FLOOR TO 19TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PUTTY WORKS IN PROGRESS
TOWER - 3 • DADO WORKS COMPLETED • VITRIFIED TILING WORKS COMPLETED • LIFT LOBBY WORKS COMPLETED • 100% IPS FLOORING WORKS COMPLETED • KITCHEN & TOILET COUNTER WORK IN PROGRESS • 1 ST TO 19TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 4 • RAILING WORKS IN PROGRESS • 85% EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 48/75 FLATS DADO WORKS COMPLETED • 42/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 2 ND TO 12TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 5 • RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER COMPLETED • 70/75 FLATS IPS FLOORING WORKS COMPLETED • 72/75 FLATS DADO WORKS COMPLETED • 64/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 6 • RAILING WORKS COMPLETED • INTERNAL PLASTER WORKS IN PROGRESS • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 70/75 FLATS DADO WORKS COMPLETED • 68/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 2 ND TO 18TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER-1 GROUND FLOOR RECEPTION
FEATURE WALL
TOWER-2 GROUND FLOOR LIFT LOBBY
BOUNDARY WALL RAILING WORKS IN PROGRESS
EXTERNAL DEVELOPMENT
EXTERNAL DEVELOPMENT
PODIUM WORKS IN PROGRESS
PODIUM WORKS IN PROGRESS