Park Generations Construction Update Nov 2017

PARK GENERATIONS
TOWER – 1 • 95% EXTERNAL PLASTER WORKS COMPLETED. • TYP. LIFT LOBBY FLOORING & CLADDING WORKS COMPLETED IN 19 OUT OF 20 FLOORS • PUTTY WORKS IN PROGRESS AND DONE FROM 1ST TO 19TH FLOOR SINGLE COAT
TOWER – 2 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • VITRIFIED FLOORING IN 71 FLATS OUT OF 75 COMPLETED. • TYP. LIFT LOBBY FLOORING & CLADDING WORKS IN PROGRESS. • PUTTY WORKS IN PROGRESS AND DONE FROM
TOWER – 3 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • 95% IPS FLOORING COMPLETED. • DADO WORK IN 40 FLATS OUT OF 75 COMPLETED.
TOWER – 4 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 80% EXTERNAL PLASTER WORKS COMPLETED. • 74/75 FLATS IPS FLOORING COMPLETED. • DADO WORK IN 30 FLATS OUT OF 75 COMPLETED.
TOWER – 5 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 90% EXTERNAL PLASTER WORKS COMPLETED. • 74/75 FLATS IPS FLOORING COMPLETED. • DADO WORK IN 27 FLATS OUT OF 75 COMPLETED. • VITRIFIED FLOORING WORKS 34 FLATS OUT OF 75 COMPLETED
TOWER – 6 • INTERNAL PLASTER WORKS ALMOST COMPLETED. • 95% EXTERNAL PLASTER WORKS COMPLETED. • 72/75 FLAT IPS FLOORING COMPLETED. • DADO WORK IN 56 FLATS OUT OF 75 COMPLETED. • VITRIFIED FLOORING IN 42 FLATS OUT OF 75 COMPLETED.