Spacio Construction Update Jan 2018

TOWER-K • 95% RAILING WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS • 17TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 65% EXTERNAL PLASTER WORKS COMPLETED. • 11TH FLOOR IPS FLOORING WORKS COMPLETED.
TOWER-L • 80% RAILING WORKS COMPLETED. • EXTERNAL PLASTER WORKS IN PROGRESS. • 18TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 40% EXTERNAL PLASTER WORKS COMPLETED.
TOWER-M • 16TH FLOOR BRICK WORKS IN PROGRESS. • 12TH FLOOR INTERNAL PLASTER WORKS COMPLETED.
TOWER-N • 90% RAILING WORKS COMPLETED. • INTERNAL PLASTER WORKS COMPLETED. • 60% EXTERNAL PLASTER WORKS COMPLETED. • 03RD FLOOR IPS FLOORING WORKS COMPLETED.
TOWER-P • 80% RAILING WORKS COMPLETED. • 16TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 50% EXTERNAL PLASTER WORKS COMPLETED.
TOWER-Q • 85% BALCONY RAILING WORKS COMPLETED. • INTERNAL PLASTER WORKS COMPLETED. • 35% EXTERNAL PLASTER WORKS IN PROGRESS. • 06TH FLOOR IPS FLOORING WORKS COMPLETED.
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT