Spacio Construction Update May 2018

TOWER-K • 90% BALCONY RAILING WORKS COMPLETED • 80% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 11th FLOOR IPS FLOORING WORKS COMPLETED
TOWER-L • 90% BALCONY RAILING WORKS COMPLETED • 50% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 2 FLOOR IPS FLOORING WORKS COMPLETED
TOWER-M • 20% BALCONY RAILING WORKS COMPLETED • 16th FLOORS INTERNAL PLASTER WORKS COMPLETED • 5% EXTERNAL PLASTER WORKS COMPLETED
TOWER-N • 90% BALCONY RAILING WORKS COMPLETED • 75% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 3 rd FLOOR IPS FLOORING WORKS COMPLETED
TOWER-P • 70% BALCONY RAILING WORKS COMPLETED • 55% EXTERNAL PLASTER WORKS COMPLETED • 18TH FLOOR INTERNAL PLASTER WORKS COMPLETED
TOWER-Q • 60% BALCONY RAILING WORKS COMPLETED • 40% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 6 TH FLOOR IPS FLOORING WORKS COMPLETED
HARD LANDSCAPING WORKS IN PROGRESS
37 D CLUB & SWIMMING POOL WORKS IN PROGRESS
TOWER N - SAMPLE FLAT
TOWER N - SAMPLE FLAT