Spacio Construction Update Nov 2017

SPACIO
TOWER-K - 80% BALCONY RAILING WORKS COMPLETED. • 35% EXTERNAL PLASTER WORKS COMPLETED. • 17TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 8TH FLOOR IPS FLOORING WORKS COMPLETED.
TOWER-L - BRICK WORKS COMPLETED. • 50% BALCONY RAILING WORKS COMPLETED. • 20% EXTERNAL PLASTER WORKS COMPLETED. • 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED.
TOWER-M - 18TH FLOOR STRUCTURE WORKS COMPLETED. • 12TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 13TH FLOOR BRICK WORKS COMPLETED.
TOWER-N - 50% BALCONY RAILING WORKS COMPLETED. • 18TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 30% EXTERNAL PLASTER WORKS COMPLETED.
TOWER-P - 40% BALCONY RAILING WORKS COMPLETED. • 14TH FLOOR INTERNAL PLASTER WORKS COMPLETED.
TOWER-Q - 50% BALCONY RAILING WORKS COMPLETED. • 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 20% EXTERNAL PLASTER WORKS COMPLETED.