Spacio Construction Update Oct 2017

SPACIO
TOWER-K - BRICK WORKS COMPLETED. • 40% BALCONY RAILING WORKS COMPLETED. • 15% EXTERNAL PLASTER WORKS COMPLETED. • 16TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 8 TH FLOOR IPS FLOORING WORKS COMPLETED.
TOWER-L - BRICK WORKS COMPLETED. • 40% BALCONY RAILING WORKS COMPLETED. • 20% EXTERNAL PLASTER WORKS COMPLETED. • 12TH FLOOR INTERNAL PLASTER WORKS COMPLETED.
TOWER-M - 17TH FLOOR STRUCTURE WORKS COMPLETED. • 12TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 13TH FLOOR BRICK WORKS IN PROGRESS.
TOWER-N - STRUCTURE WORKS COMPLETED. • BRICK WORKS COMPLETED. • 40% BALCONY RAILING WORKS COMPLETED. • 16TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 15% EXTERNAL PLASTER WORKS COMPLETED.
TOWER-P - STRUCTURE WORKS COMPLETED. • BRICK WORKS COMPLETED. • 12TH FLOOR INTERNAL PLASTER WORKS COMPLETED.
TOWER-Q - STRUCTURE WORKS COMPLETED. • BRICK WORKS COMPLETED. • 40% BALCONY RAILING WORKS COMPLETED. • 13TH FLOOR INTERNAL PLASTER WORKS COMPLETED. • 15% EXTERNAL PLASTER WORKS COMPLETED.