Terra Construction Update April 2018

FRONT ELEVATION
TOWER – 20 RAILING AND INTERNAL & EXTERNAL PLASTER WORKS IN PROGRESS
TOWER – 21 RAILING AND INTERNAL & EXTERNAL PLASTER WORKS IN PROGRESS
TOWER – 22 2ND TO 12TH FLOOR BRICK WORKS COMPLETED AND RAILING & INTERNAL PLASTER WORKS IN PROGRESS
TOWER – 23 2 ND TO 14TH FLOOR BRICK WORKS COMPLETED AND RAILING & INTERNAL PLASTER WORKS IN PROGRESS
TOWER – 24 RAILING AND INTERNAL & EXTERNAL PLASTER WORKS IN PROGRESS
TOWER – 25 RAILING AND INTERNAL & EXTERNAL PLASTER WORKS IN PROGRESS
TOWER 22 & 23 CONDUITING WORKS IN PROGRESS
TOWER 22 & 23 REINFORCEMENT WORKS IN PROGRESS
TOWER 22 & 23 REINFORCEMENT WORKS IN PROGRESS
BASEMENT ROOF SHUTTERING WORKS IN PROGRESS