Terra Construction Update May 2018

FRONT ELEVATION
TOWER – 20 • FACIA RAILING WORKS IN PROGRESS • 70% EXTERNAL PLASTER WORKS COMPLETED • 15TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 16TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS
TOWER – 21 • FACIA RAILING WORKS IN PROGRESS • 50% EXTERNAL PLASTER WORKS COMPLETED • 9 TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 10TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS
TOWER – 22 • 16TH FLOOR SLAB CASTED • 2 ND TO 10TH FLOOR BRICK WORKS COMPLETED • FACIA RAILING WORKS IN PROGRESS • 11TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 12TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS
TOWER – 23 • 16TH FLOOR SLAB CASTED • 2 ND TO 10TH FLOOR BRICK WORKS COMPLETED • FACIA RAILING WORKS IN PROGRESS • 3 RD FLOOR INTERNAL PLASTER WORKS COMPLETED • 4 TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS
TOWER – 24 • FACIA RAILING WORKS IN PROGRESS • 50% EXTERNAL PLASTER WORKS COMPLETED • 14TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 15TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS
TOWER – 25 • FACIA RAILING WORKS IN PROGRESS • 60% EXTERNAL PLASTER WORKS COMPLETED • 17TH FLOOR INTERNAL PLASTER WORKS COMPLETED • 18TH FLOOR INTERNAL PLASTER WORKS IN PROGRESS
BASEMENT COLUMN CASTING WORKS IN PROGRESS
TOWER 22 & 23 COLUMN STEEL BINDING AND SHUTTERING WORKS IN PROGRESS
TOWER 22 & 23 COLUMN STEEL BINDING AND SHUTTERING WORKS IN PROGRESS
STP RAFT STEEL BINDING WORKS IN PROGRESS