Slideshow Image 1

Visionnaire Villas Construction Update Jan 2018

A 19 TO 21 STRUCTURE COMPLETE AND BLOCK WORKS IN PROGRESS
B 87 TO 91 SHUTTERING WORKS IN PROGRESS
B 168 TO 184 RCC AND BLOCK WORKS IN PROGRESS
A 19 TO 21 BLOCK WORKS UNDER COMPLETION
A 19 TO 21 BLOCK WORKS UNDER COMPLETION
B 191 TO 197 BLOCK WORKS IN PROGRESS
B 185 A & B 185 RCC WORKS IN PROGRESS
RCC AND FOUNDATION WORKS IN PROGRESS