Visionnaire Villas Construction Update June 2018

MAIN ENTRANCE – FINISHING WORKS IN PROGRESS
A-19 TO A-21 EXTERNAL PLASTER AND BLOCK WORKS IN PROGRESS
B-87 TO B-88 RCC WORKS IN PROGRESS
B-89 TO B-91 RCC WORKS IN PROGRESS
B-161 TO B-167 RCC & BLOCK WORKS IN PROGRESS
B-168 TO B-185 RCC & BLOCK WORKS IN PROGRESS
B-185 A & B-185B RCC WORKS IN PROGRESS
B-189 TO B-199 RCC, PLASTER AND BLOCK WORKS IN PROGRESS
PARK - 01
PARK - 01
PARK 04 STONE, PATHWAY GRIT WASH & EARTH WORKS IN PROGRESS