Capital City Construction Update April 2018

SCAFFOLDING FOR NORTH ELEVATION IN PROGRESS
BACKFILLING IN PROGRESS FOR FACADE STONE YARD
BASEMENT 3 RETAINING WALL AND SLAB 50% COMPLETE
BRICKWORK AND PLASTER ON TERRACE COMMENCED
COLUMN STRENGTHENING FOR THE ATRIUM POOL STRUCTURE
JCB EXCAVATION IN BASEMENT- PREPARATION FOR DG FOUNDATION
KOTA FLOORING ON STAIRCASE- 75% COMPLETE
SCREED WORKS IN PROGRESS 6TH FLOOR- 50% COMPLETE
TRIMIX 85% COMPLETE IN BASEMENT