Discovery Park Construction Update Sep 2018

TOWER - K • 56/56 FLATS TOILET FLOORING WORKS COMPLETED AND 56/56 D&D TILING WORKS COMPLETED, 15/15 LOBBY TILING WORKS COMPLETED. • 168/168 NOS. BALCONY CILL STONE WORKS COMPLETED • 56/56 FLATS KITCHEN COUNTER STONE WORKS COMPLETED • 95% STAIRCASE KOTA STONE WORKS COMPLETED • 56/56 FLATS WOODEN POLISH (SINGLE COAT) WORKS COMPLETED • 56/56 FLATS OBD 1 COAT (INTERNAL) WORKS COMPLETED • 95% PRIMER WORKS COMPLETED
TOWER - J • 86/86 FLATS TOILET FLOORING WORKS COMPLETED AND 86/86 D&D TILING WORKS COMPLETED, 15/15 LOBBY TILING WORKS COMPLETED. • 258/258 NOS. BALCONY CILL STONE WORKS COMPLETED • 86/86 FLATS KITCHEN COUNTER STONE WORKS COMPLETED • 95% STAIRCASE KOTA STONE WORKS COMPLETED • 80/86 FLATS WOODEN POLISH (SINGLE COAT) WORKS COMPLETED • 70/86 FLATS OBD 1 COAT (INTERNAL) WORKS COMPLETED • 95% PRIMER WORKS COMPLETED • 95% UPVC DOOR & WINDOWS WORKS COMPLETED • 83/86 FLATS WIRING WORKS COMPLETED
TOWER – H • 90/90 FLATS TOILET FLOORING WORKS COMPLETED AND 90/90 D&D TILING WORKS COMPLETED, 15/15 LOBBY TILING WORKS COMPLETED. • 100% STAIRCASE KOTA STONE WORKS COMPLETED • 85/90 FLATS WOODEN POLISH (SINGLE COAT) WORKS COMPLETED • 75/90 FLATS OBD 1 COAT (INTERNAL) WORKS COMPLETED • 95% PRIMER WORKS COMPLETED • 95% UPVC DOOR & WINDOWS WORKS COMPLETED • 90/90 FLATS WIRING WORKS COMPLETED
TOWER - G • 90/90 FLATS TOILET FLOORING WORKS COMPLETED AND 90/90 D&D TILING WORKS COMPLETED, 15/15 LOBBY TILING WORKS COMPLETED. • 100% STAIRCASE KOTA STONE WORKS COMPLETED • 80/90 FLATS WOODEN POLISH (SINGLE COAT) WORKS COMPLETED • 66/90 FLATS OBD 1 COAT (INTERNAL) WORKS COMPLETED • 95% PRIMER WORKS COMPLETED • 95% UPVC DOOR & WINDOWS WORKS COMPLETED • 90/90 FLATS WIRING WORKS COMPLETED
TOWER - F • 90/90 FLATS TOILET FLOORING WORKS COMPLETED AND 90/90 D&D TILING WORKS COMPLETED, 15/15 LOBBY TILING WORKS COMPLETED. • 100% STAIRCASE KOTA STONE WORKS COMPLETED • 90/90 FLATS WOODEN POLISH (SINGLE COAT) WORKS COMPLETED • 60/90 FLATS OBD 1 COAT (INTERNAL) WORKS COMPLETED • 95% PRIMER WORKS COMPLETED • 90% UPVC DOOR & WINDOWS WORKS COMPLETED • 90/90 FLATS WIRING WORKS COMPLETED
TOWER - L 12TH FLOOR SLAB WORKS COMPLETED. 1 ST TO 9TH FLOOR BRICK WORKS COMPLETED.
TOWER - M 13TH FLOOR SLAB CASTED. 1 ST TO 10TH FLOOR BRICK WORKS COMPLETED.
TOWER - A • TERRACE SLAB CASTED • GROUND TO 14TH FLOOR BRICK WORKS COMPLETED • 285/300 RAILING WORKS COMPLETED • 78/88 FLATS INTERNAL PLASTER WORKS COMPLETED • 80% EXTERNAL PLASTER WORKS COMPLETED • 24/88 FLATS IPS FLOORING WORKS COMPLETED • STONE FIXING WORKS IN PROGRESS
TOWER - B • TERRACE SLAB CASTED • 1 ST TO 16TH FLOOR BRICK WORKS COMPLETED • 305/532 RAILING WORKS COMPLETED • 136/142 FLATS INTERNAL PLASTER WORKS COMPLETED • 70% EXTERNAL PLASTER WORKS COMPLETED • STONE FIXING WORKS IN PROGRESS
CLUB STRUCTURE & BLOCK WORKS IN PROGRESS
MAIN ENTRY WORKS IN PROGRESS
GUARD ROOM AT MAIN ENTRANCE
LANDSCAPING WORKS IN PROGRESS
MAIN ENTRY WATERBODY WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS