Park 81 Construction Update April 2019

81 AVE - 07 TO12 PARKING WORKS IN PROGRESS
81 AVE - 39 TO 42 INTERNAL & EXTERNAL PLASTER, TILES AND STAIRCASE STONE FIXING WORKS IN PROGRESS
CL2 - 01 TO 06 UPVC DOOR & WINDOWS FIXING AND PARKING PAVER WORKS IN PROGRESS
CL2 - 07 TO 12 PARKING PAVER WORKS IN PROGRESS
CL3 - 01 TO 06 GRADE SLAB PARKING PAVER WORKS IN PROGRESS
CL3-07 TO 12 UPVC DOOR & WINDOW FIXING AND GRADE SLAB WORKS IN PROGRESS
OMEGA 12 - 01 TO 06 TILE FIXING WORKS IN PROGRESS
OMEGA 13 - 01 TO 05 TILE FIXING AND IPS FLOORING WORKS IN PROGRESS
VL1 -11 TO 19 IPS FLOORING, UPVC DOOR & WINDOW AND TILES FIXING WORKS IN PROGRESS
VL1 - 12 TO 20 UPVC DOOR & WINDOW FIXING AND INTERNAL PLASTER WORKS IN PROGRESS