Park 81 Construction Update December 2018

81 AVE 7-11 INTERNAL PAINTING WORKS IN PROGRESS
81 AVE 35 TO 42 PARKING WORKS IN PROGRESS
CL02-01 TO 06 PLASTER, TILES AND STONE WORKS IN PROGRESS
CL02-07 TO 12 DRIVEWAY GRADE SLAB PLASTER WORKS IN PROGRESS
CL03-01 TO 06 STONE FIXING, EXTERNAL & INTERNAL PLASTER WORKS IN PROGRESS
CL3-07 TO 12 TILES, STONE AND ELECTRIC TRENCH PCC WORKS IN PROGRESS
OMEGA 12-1 TO 6 FLOORING WORKS IN PROGRESS
OMEGA 13-1 TO 5 IPS FLOORING WORKS IN PROGRESS
VL01-11 - 19 TILES, EXTERNAL & INTERNAL PLASTER WORKS IN PROGRESS
VL1-12 TO 20 MS FRAME FIXING WORKS IN PROGRESS