Park Elite Floors I and II Construction Update January 2019

P Block

P-02 TO P-07F PLASTER, TILE, WATER PROOFING AND BRICK WORKS IN PROGRESS
P5-01 TO P5-08 WOODEN FLOORING, PAINT, PLUMBING AND ELECTRICAL WORKS IN PROGRESS
P5-09 TO P5-12 WOODEN FLOORING AND FINAL FINISHING WORKS IN PROGRESS
P7-01 TO P7-23 PARKING, PAINTING, PLUMBING AND ELECTRICAL WORKS IN PROGRESS
P9-02 TO P9-10 PLUMBING, PAINT, ELECTRICAL AND PLASTER WORKS IN PROGRESS
P15-12 TO P15-16 PAINTING, PLUMBING AND ELECTRICAL WORKS IN PROGRESS
P16-02 TO P16-10 PLUMBING, ELECTRICAL AND PAINTING WORKS IN PROGRESS
P17-01 TO P17-04 PLUMBING, PAINT AND ELECTRICAL WORKS IN PROGRESS

PE Block

PE 31 FF PAINTING WORKS IN PROGRESS
PE 31 GF KITCHEN TILE CLEANING WORKS IN PROGRESS
PE 37 GF INTERNAL TILE CLEANING WORKS IN PROGRESS
PE 37 GF TILE GROUTING WORKS IN PROGRESS
PE 37 GF UPVC CLEANING WORKS IN PROGRESS
PE 75 - 83 PARKING AREA WORKS IN PROGRESS
PE 86 – 95 PLASTER WORKS IN PROGRESS
PE 87 FRONT BOUNDARY WALL BRICK WORKS IN PROGRESS
PE 154 – PE 156 PLASTER WORKS IN PROGRESS
PE 154 EXTERNAL PLASTER WORKS IN PROGRESS
PE 179 – 190 FINISHING WORKS IN PROGRESS
PE 191 -202 EXTERNAL PLASTER WORKS IN PROGRESS
PE 196 FRONT SIDE CHICKEN WIRE MESH FIXING WORKS IN PROGRESS
PE 197 EXTERNAL PLASTER WORKS IN PROGRESS
PE 198 EXTERNAL PLASTER WORKS IN PROGRESS
PE 300 – 315 UPVC DOOR & WINDOWS FIXING WORKS IN PROGRESS
PE 304 1ST FLOOR VITRIFIED TILES FIXING WORKS IN PROGRESS
PE 312 – 313 STAIR CASE KOTA STONE FIXING WORK IN PROGRESS
PE 314 -315 STAIR CASE KOTA STONE WORKS IN PROGRESS
PE 338 – 353 PLASTER WORKS IN PROGRESS
PE 338 – 353 PLASTER WORKS IN PROGRESS
PE 340 SF INTERNAL PLASTER WORKS IN PROGRESS
PE 342 1ST FLOOR CONDUITING WORKS IN PROGRESS

M Block

M10 - 04 TO 12 EXTERNAL PAINTING WORKS IN PROGRESS
M10-04 TO 12 FALSE CEILING WORKS IN PROGRESS
M10-04 TO 12 KOTA GRINDING WORKS IN PROGRESS
M10 - 03 TO 12 EXTERNAL PLASTER WORKS IN PROGRESS