Park Elite Floors I and II Construction Update Sep 2018

E Block

E40-24 TO 46 EXTERNAL & INTERNAL PLASTER WORKS IN PROGRESS
E40-27 GF KOTA FIXING WORKS IN PROGRESS
E40-34 RAILING FIXING WORKS IN PROGRESS
E40-34 TILE SKIRTING WORKS IN PROGRESS
E40-34 UPVC WINDOWS AND DOOR FIXING WORKS IN PROGRESS

H Block

H4-1TO21 CABLE TRENCH WORKS IN PROGRESS
H3-11 TO 17 EXTERNAL & INTERNAL PAINT WORKS IN PROGRESS
H4-16 PERGOLA PLASTER WORKS IN PROGRESS
H6-17 FLOORING, EXTERNAL & INTERNAL PAINT WORKS IN PROGRESS
H6-17 KITCHEN COUNTER FIXING WORKS IN PROGRESS

M Block

M10-ROW (M10-03 TO 12) FINISHING WORKS IN PROGRESS
M10-04 TO 12 FIXING OF KOTA STONE IN STAIRCASE WORKS IN PROGRESS
M10-03 TO 11 INTERNAL PAINTING WORKS IN PROGRESS
M10-03 TO 11 INTERNAL WIRING WORKS IN PROGRESS

PA Block

PA-228 TO PA-241 GRADE SLAB WORK AND TERRACE KOBA WORKS IN PROGRESS
PA-242 TO 247 GF GRADE SLAB WORKS IN PROGRESS

PC Block

PC-60 TO 76 OOP ALREADY ISSUED
PC-77 TO 93 OOP ALREADY ISSUED
PC-37 TO 53 EXTERNAL CONNECTION, INTERNAL FLOORING AND INTERNAL PAINTING WORKS IN PROGRESS