Park Elite Premium Construction Update January 2019

TOWER- A • 80% TERRACING WORKS COMPLETED. • 60/60 UNITS IPS FLOORING WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 60% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- B • 40/40 UNITS IPS FLOORING WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 60% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- C • 95% EXTERNAL PLASTER WORKS COMPLETED. • 5% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 60% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- D • 98% EXTERNAL PLASTER WORKS COMPLETED. • 40/40 UNITS IPS FLOORING WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 5% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS • 60% LIFT WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- G • 100% EXTERNAL PLASTER WORKS COMPLETED. • 60% STONE & TILES WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 10% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 10% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- J • 100% EXTERNAL PLASTER WORKS COMPLETED. • 60% STONE & TILES WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 20% INTERNAL WIRING WORKS COMPLETED. • 10% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 10% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- K • 100% EXTERNAL PLASTER WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 60% STONE & TILES WORKS COMPLETED. • 10% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 10% LIFT WORKS COMPLETED. • 50% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
EWS TOWER • 100% EXTERNAL PLASTER WORKS COMPLETED. • 56/56 UNITS IPS FLOORING WORKS COMPLETED. • 25% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
VILLAS 10-19 • 95% INTERNAL PLASTER WORKS COMPLETED. • 100% EXTERNAL PLASTER WORKS COMPLETED. • 100% IPS FLOORING WORKS COMPLETED. • 50% STONE & TILES WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
CLUB FALSE CEILING WORKS IN PROGRESS
LAP POOL WORKS IN PROGRESS
TENNIS COURT WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS
CENTRAL PARK HARDSCAPING WORKS IN PROGRESS