Park Elite Premium Construction Update March 2019

TOWER- A • 80% TERRACING WORKS COMPLETED. • 60/60 UNITS IPS FLOORING WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 75% LIFT WORKS COMPLETED. • 75% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- B • 40/40 UNITS IPS FLOORING WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 75% LIFT WORKS COMPLETED. • 75% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- C • 95% EXTERNAL PLASTER WORKS COMPLETED. • 20% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 15% INTERNAL WIRING WORKS COMPLETED. • 60% LIFT WORKS COMPLETED. • 75% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- D • 98% EXTERNAL PLASTER WORKS COMPLETED. • 40/40 UNITS IPS FLOORING WORKS COMPLETED. • 80% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY AND PAINT WORKS COMPLETED. • 75% FIRE FIGHTING WORKS • 75% LIFT WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- G • 60% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 20% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- J • 60% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 20% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
TOWER- K • 60% STONE & TILES WORKS COMPLETED. • 20% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 30% INTERNAL WIRING WORKS COMPLETED. • 25% LIFT WORKS COMPLETED. • 50% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
EWS TOWER • 25% INTERNAL PUTTY/PAINT WORKS COMPLETED. • 20% LIFT WORKS COMPLETED. • 60% FIRE FIGHTING WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
VILLAS 10-19 • 95% INTERNAL PLASTER WORKS COMPLETED. • 50% STONE & TILES WORKS COMPLETED. • 80% EXTERNAL STORM, SEWERAGE & WATER SUPPLY WORKS COMPLETED.
HORTICULTURE WORKS IN PROGRESS
HORTICULTURE WORKS IN PROGRESS
GAZIBO WORKS IN PROGRESS
GRIT WASH WORKS IN PROGRESS
FIRE STAIRCASE WORKS IN PROGRESS
HARD LANDSCAPING WORKS IN PROGRESS
POOL WORKS IN PROGRESS
TENNIS COURT WORKS IN PROGRESS
PATHWAY WORKS IN PROGRESS
FALSE CEILING WORKS IN PROGRESS AT CLUB
FALSE CEILING WORKS IN PROGRESS AT CLUB
CLUB HOUSE FINISHING WORKS IN PROGRESS