Amstoria Construction Update Sep 2018

NPR ACCESS ENTRANCE READY
MAIN GATE - GERMAN IMPORTED VM ZINC PANEL ON TOP
A 22 TO 27 ROW OC VISITS GOING ON
A 48 TO 53 ROW BUILT-UP 3M GREEN AREA SOFTSCAPE WORKS IN PROGRESS
A 61 TO 66 OOP GIVEN
D126 TO 135 OC VISITS GOING ON
D126 TO 135 OC VISITS GOING ON
D126 TO 135 OC VISITS GOING ON
EXTERNAL DEVELOPMENT C BLOCK
PARK 1 COMPLETED
PARK 2 COMPLETED WITH KIDS PLAY AREA, BRAZIL TEAK WOOD PERGOLA AND MULTIPURPOSE COURT ETC
PARK 3 TENNIS COURT
CLUB HOUSE – BUILDING STRUCTURE WORKS IN PROGRESS