Park Generations Construction Update December 2018

TOWER - 1 OC RECEIVED
TOWER - 2 OC RECEIVED
TOWER - 3 OC RECEIVED
TOWER - 4 • 95% EXTERNAL PLASTER COMPLETED • IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 73/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 17TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 5 • 100% EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 75/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • GROUND TO 14TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS • LIFT LOBBY CLADDING WORKS IN PROGRESS
TOWER - 6 • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 75/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 19TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS • LIFT LOBBY FLOORING WORKS COMPLETED
APHITHEATRE AT GENERATION
FEATURE WALL
ENTRANCE TOWER 1
EXTERNAL DEVELOPMENT
EXTERNAL DEVELOPMENT
FIRE TENDER PATH
PODIUM LEVEL
TOP VIEW
TOWER-1 ENTRANCE
TOWER-2 ENTRANCE
PODIUM
HORTICULTURE WORKS IN PROGRESS
EXTERNAL DEVELOPMENT
PARKING AREA
STILT LEVEL TOWER - 1
Bird eye View Podium Level Generation