Park Generations Construction Update January 2019

TOWER 2, 3, 4 & 5 ELEVATION
TOWER - 1 OC RECEIVED
TOWER - 2 OC RECEIVED
TOWER - 3 OC RECEIVED
TOWER - 4 • 95% EXTERNAL PLASTER COMPLETED • IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 73/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 17TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS
TOWER - 5 • 100% EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 75/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • GROUND TO 14TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS • LIFT LOBBY CLADDING WORKS IN PROGRESS
TOWER - 6 • EXTERNAL PLASTER COMPLETED • 74/75 FLATS IPS FLOORING WORKS COMPLETED • 75/75 FLATS DADO WORKS COMPLETED • 75/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED • 1 ST TO 19TH FLOOR INTERNAL PUTTY WORK COMPLETED • EXTERNAL PAINT & PUTTY WORKS IN PROGRESS • LIFT LOBBY FLOORING WORKS COMPLETED
AMPHITHEATRE AT GENERATIONS
ARCHITECTURE FEATURE AT PODIUM LEVEL
FEATURE WALL
BASEMENT VENTILATION DUCTING
GLASS PANEL AT ENTRANCE LOBBY TOWER 1
PODIUM AT GENERATIONS
PLANTATION WORKS
STILT LEVEL ENTRANCE FROM TOWER 1
PODIUM LEVEL AT GENERATIONS