Park Generations Construction Update July 2018

PODIUM VIEW OF GENERATIONS
TOWER - 1 COMPLETED
TOWER - 2 KITCHEN COUNTER WORK COMPLETED & TOILET COUNTER WORK IN PROGRESS. GROUND FLOOR TO 19TH FLOOR 2 COAT INTERNAL PUTTY WORK IN PROGRESS. EXTERNAL TEXTURE WORK IN PROGRESS.
TOWER - 3 KITCHEN COUNTER WORK COMPLETED & TOILET COUNTER WORK IN PROGRESS. 1ST TO 19TH FLOOR 2 COAT INTERNAL PUTTY WORK IN PROGRESS. EXTERNAL TEXTURE WORK IN PROGRESS.
5TOWER - 4 RAILING WORKS COMPLETED EXCEPT STAIRCASE. BRICKWORK COMPLETE. 90% EXTERNAL PLASTER COMPLETED. INTERNAL PLASTER WORK COMPLETE EXCEPT IN 1 GF UNIT. 74/75 FLATS IPS FLOORING WORKS COMPLETED. 71/75 FLATS DADO WORKS COMPLETED. 62/75 FLATS VITRIFIED TILES FLOORING WORKS COMPLETED. 2ND TO 15TH FLOOR SINGLE COAT INTERNAL PUTTY WORK COMPLETED. EXTERNAL PAINT & PUTTY WORK IN PROGRESS.
TOWER - 5 EXTERNAL PLASTER COMPLETED. INTERNAL PLASTER WORK COMPLETED. 74/75 FLATS IPS FLOORING WORKS COMPLETED. 74/75 FLATS DADO WORK COMPLETED. 74/75 FLATS VITRIFIED TILES FLOORING WORK COMPLETED. 1st COAT PUTTY IN PROGRESS AND DONE UPTO 10th FlOOR. EXTERNAL PAINT PUTTY WORK IN PROGRESS.
TOWER - 6 RAILING WORKS COMPLETED. INTERNAL PLASTER COMPLETED EXCEPT 1 GF UNIT. EXTERNAL PLASTER COMPLETED. 74/75 FLATS IPS FLOORING WORK COMPLETED. 74/75 FLATS DADO WORK COMPLETED. 74/75 FLATS VITRIFIED TILES FLOORING WORK COMPLETED. PUTTY 2nd COAT IS IN PROGRESS & DONE UPTO 10th FLOOR. EXTERNAL PAINT & PUTTY WORKS IN PROGRESS.
BOUNDARY WALL LANDSCAPING WORK IN PROGRESS
FEATURE WALL IN FRONT OF TOWER 1
EXTERNAL DEVELOPMENT
PARKING AREA
INSTALLATION OF 33KvA TRANSFORMERS
INTERIOR WORK OF LOBBY IN PROGRESS
PODIUM LANDSCAPE