Spacio Construction Update August 2018

TOWER-K • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19th FLOOR IPS FLOORING WORKS COMPLETED • 3 FLOORS TILES/STONE FIXING WORKS IS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-L • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19th FLOOR IPS FLOORING WORKS COMPLETED • 2 FLOORS TILES/STONE FIXING WORKS IS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-M • 50% BALCONY RAILING WORKS COMPLETED • 50% EXTERNAL PLASTER WORKS COMPLETED • 18th FLOOR INTERNAL PLASTER WORKS COMPLETED • 13th FLOOR IPS FLOORING WORKS COMPLETED
TOWER-N • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 12th FLOOR IPS FLOORING WORKS COMPLETED • 2 FLOORS TILES/STONE FIXING WORKS IS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-P • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • IPS FLOORING WORKS IN PROGRESS • TILES/STONE FIXING WORKS IN PROGRESS
TOWER-Q • 95% BALCONY RAILING WORKS COMPLETED • 60% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 9 th FLOOR IPS FLOORING WORKS COMPLETED
LANDSCAPING WORKS IN PROGRESS
LANDSCAPING WORKS IN PROGRESS