In order to give you a better experience, we are renovating our website. However, please note that the data mentioned on the website is still being updated. For accurate and upto date information, please contact our team at customercare@bptp.com.
In order to give you a better experience, we are renovating our website. However, please note that the data mentioned on the website is still being updated. For accurate and upto date information, please contact our team at customercare@bptp.com.
Slideshow Image 1

Spacio Construction Update January 2019

TOWER-K • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19th FLOOR IPS FLOORING WORKS COMPLETED • 8 th FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-L • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED • 8 TH FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-M • 60% BALCONY RAILING WORKS COMPLETED • 18th FLOORS INTERNAL PLASTER WORKS COMPLETED • 60% EXTERNAL PLASTER WORKS COMPLETED • 14TH FLOOR IPS FLOORING WORKS COMPLETED
TOWER-N • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED • 8 TH FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-P • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • IPS FLOORING WORKS IN PROGRESS • TILES/STONE FIXING WORKS IN PROGRESS
TOWER-Q • 95% BALCONY RAILING WORKS COMPLETED • 60% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 9 TH FLOOR IPS FLOORING WORKS COMPLETED
EXTERNAL BRICK WORKS IN PROGRESS
HORTICULTURE WORKS IN PROGRESS
HORTICULTURE WORKS IN PROGRESS
SAMPLE FLAT