Spacio Construction Update May 2019

TOWER-K • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19th FLOOR IPS FLOORING WORKS COMPLETED • 15th FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-L • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED • 13TH FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-M • 60% BALCONY RAILING WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED
TOWER-N • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED • 17th FLOOR TILES/STONE FIXING WORKS COMPLETED • PUTTY/PAINT WORKS IN PROGRESS
TOWER-P • 95% BALCONY RAILING WORKS COMPLETED • 95% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • IPS FLOORING WORKS IN PROGRESS • TILES/STONE FIXING WORKS IN PROGRESS
TOWER-Q • 95% BALCONY RAILING WORKS COMPLETED • 85% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 19TH FLOOR IPS FLOORING WORKS COMPLETED
HORTICULTURE WORKS IN PROGRESS
CLUB HOUSE
SWIMMING POOL TILE FIXING WORKS IN PROGRESS
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT
SAMPLE FLAT