Terra Construction Update March 2019

TOWER – 20 • 90% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 72/76 UNITS IPS FLOORING WORKS COMPLETED • 8/76 UNITS TILE/STONE WORKS COMPLETED
TOWER – 21 • 90% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 72/76 UNITS IPS FLOORING WORKS COMPLETED
TOWER – 22 • 100% STRUCTURE COMPLETED • 2 ND TO 17TH FLOOR BRICK WORKS COMPLETED, 18TH FLOOR BRICK WORKS IN PROGRESS • 2 ND TO 17TH FLOOR INTERNAL PLASTER WORKS COMPLETED
TOWER – 23 • STRUCTURE WORKS COMPLETED • 3 RD TO 17TH FLOOR BRICK WORKS COMPLETED, 18TH FLOOR BRICK WORKS IN PROGRESS • 2 ND TO 10TH FLOOR INTERNAL PLASTER WORKS COMPLETED
TOWER – 24 • 85% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 58/76 FLAT IPS FLOORING WORKS COMPLETED
TOWER – 25 • 85% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS • 72/76 UNITS IPS FLOORING WORKS COMPLETED
PODIUM STRUCTURE WORKS IN PROGRESS
SHUTTERING WORKS IN PROGRESS
SAMPLE FLAT - RAILING WORKS IN PROGRESS
SAMPLE FLAT FINISHING WORKS IN PROGRESS
SAMPLE FLAT FINISHING WORKS IN PROGRESS