Terra Construction Update November 2018

FRONT ELEVATION
TOWER – 20 • 90% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 68/76 UNITS IPS FLOORING WORKS COMPLETED • TILE/STONE WORKS IN PROGRESS
TOWER – 21 • 90% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 68/76 UNITS IPS FLOORING WORKS COMPLETED
TOWER – 22 • 100% STRUCTURE COMPLETED • 2 ND TO 17TH FLOOR BRICK WORKS COMPLETED, 18TH FLOOR BRICK WORKS IN PROGRESS • 2 ND TO 16TH FLOOR INTERNAL PLASTER WORKS COMPLETED REST IN PROGRESS
TOWER – 23 • 19TH FLOOR SLAB CASTED • 3 RD TO 17TH FLOOR BRICK WORKS COMPLETED, 18TH FLOOR BRICK WORKS IN PROGRESS • 2 ND TO 10TH FLOOR INTERNAL PLASTER WORKS COMPLETED
TOWER – 24 • 85% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS COMPLETED • 8/76 FLAT IPS FLOORING WORKS COMPLETED
TOWER – 25 • 85% EXTERNAL PLASTER WORKS COMPLETED • 100% INTERNAL PLASTER WORKS • 68/76 UNITS IPS FLOORING WORKS COMPLETED
BASEMENT SLAB CASTING WORKS IN PROGRESS